WAPA CEO Karl Knight TS Ernesto Restoration Update on August 15, 2024, at 5:00pm AST.
Video: https://youtu.be/P2TmRYu9yfE
Project Timeline: July 2022 - July 2023
Funding: Territorial Drinking Water Capital Improvement Program by the US Environmental Protection Agency (EPA)
Next Steps: Install the remaining 1000 ft of 6” and 1000 ft of 10” pipe along Rt 75 after the VI Department of Public Works project earthworks is complete to final grade. Pressure Testing and Water Quality Testing for the eastern half of Clifton Hill, followed by transfer of service and final tie-in to main line.
Estimated Cost: $4.4 million
Project Timeline: March 2023 - December 2023
Funding: Territorial Drinking Water Capital Improvement Program by the US Environmental Protection Agency (EPA). Estimated Funds: $7,295,450
What to Expect: All residents in the area should be aware of construction activities that will impact road conditions, dust and noise levels as well as some scheduled water service interruptions as the new system is installed, tested and activated.
Estimated Cost: $7.3 million
Project Timeline: February 2024- September 2024
Funding: Drinking Water State Revolving Fund (DWSRF) by Environmental ProtectionAgency (EPA) - Estimated Funds: $3,196,936
Estimated Cost : $3.3 million
Estimated Cost : TBD